Installation

The device can be installed inside an electrical panel on a DIN rail. Follow the steps below to install the device.

Note

The installation, operation, and maintenance of electrical equipment must be carried out exclusively by qualified personnel. Renua Società Benefit S.r.l. assumes no responsibility for any consequences arising from the use of this material. Qualified personnel are individuals who possess adequate skills and knowledge regarding the construction, installation, and operation of electrical equipment and who have received appropriate safety training to recognize and avoid inherent hazards. REFER TO THE Safety Information SECTION.

Mounting

The figures below illustrate how to mount and remove the device from a DIN rail:

Mounting

Figure 2 – DIN Rail Mounting and Removal

Wiring

Important Notice

All operations described in this section must be performed exclusively by qualified personnel in accordance with applicable technical and safety regulations.

Installation of the device involves interaction with mains voltages up to 400 V. Failure to comply with safety requirements may result in serious electric shock hazards, equipment damage, and risks to personnel.

The analyzer must be installed downstream of a suitably rated circuit breaker or disconnect switch, clearly identified and located near the device so that it can be easily accessed for isolation purposes.

Before starting any installation or wiring activity, ensure that the circuit breaker or disconnect switch is in the OFF position and verify the absence of voltage using a properly calibrated testing device.

🧰 Required Materials

  • RE-211 – Three-phase Energy Meter (DIN rail version)
  • DIN rail (35 mm standard)
  • Electrical cables (cross-section suitable for the load and compliant with applicable standards)
  • Screwdrivers, wire strippers, multimeter
  • Cable terminals (optional but recommended)
  • Circuit breaker (recommended between the supply line and the meter)
  • This technical manual (essential for the correct wiring diagram)

🛠️ Installation and Wiring Procedure (DIN Rail Version)

  1. Disconnect power from the system and verify the absence of voltage on the conductors using an appropriate measuring instrument (e.g., a properly calibrated and functioning multimeter).
  2. Install the RE-211-D device on a standard 35 mm DIN rail as shown in Figure 2, ensuring that it is securely attached.
  3. Connect the current input to the current transformer (CT) according to the wiring diagram, ensuring the correct correspondence between phases and inputs: L → CT
Note

This operation must be performed before mounting the CTs on the power conductors to ensure correct phase association.

  1. Mount the current transformer (CT) on the phase conductor (L).

It is essential that the directional arrow marked on each CT is oriented from the measurement point (meter or source – identified as "K") toward the load (electrical panel – identified as "L"), as illustrated in the figure below.

Note

Incorrect CT installation may compromise the accuracy of current measurements and energy flow direction detection.

CT Installation

Figure 3 – Current Transformer (CT) Installation

  1. Connect the phase voltage inputs [VOLTAGE INPUTS] according to the supplied wiring diagram. The use of a dedicated circuit breaker (2-pole, 6 A or 10 A rating, minimum breaking capacity 4.5 kA) is strongly recommended for single-phase installations. This solution improves safety, efficiency, and regulatory compliance for the following reasons:
    1. Provides adequate protection against overloads and short circuits, reducing the risk of permanent damage.
    2. Allows functional isolation of the equipment, facilitating safe maintenance, inspection, or replacement without affecting the power continuity of the installation.
    3. Meets the requirements of applicable technical standards (e.g., IEC/CEI 64-8) and aligns with industry best practices.
    4. Simplifies wiring organization, making fault identification and troubleshooting easier.
Figure 4 - RE-211-D Power Supply Connection

Figure 4 – RE-211-D Power Supply Connection

  1. Connect the [POWER INPUT] terminals to provide power to the device.

Whenever possible, it is recommended to connect the power inputs to an auxiliary or preferred power line to ensure continuous operation of the analyzer even in the event of faults or interruptions on the monitored electrical lines.

Figure 5 - RE-211 Energy Meter General Wiring

Figure 5 – RE-211 Energy Meter General Wiring

Wireless Network Connection

To ensure a stable and reliable connection, the Wi-Fi signal must be adequate and the network must have Internet access.

At first startup (or after resetting network settings), the analyzer will automatically enter Access Point (AP) mode.

Using a computer or mobile device, open the list of available Wi-Fi networks and select the network identified as RE-XXXXXX.

After connecting, follow the instructions displayed on the Wi-Fi configuration page that will automatically open in the browser of the device connected to the analyzer's Wi-Fi network.

Figure 6 - Wi-Fi Setup

Figure 6 – Wi-Fi Setup

After clicking "Scan", the available wireless networks will be displayed.

Figure 7 - Wi-Fi Scan

Figure 7 – Wi-Fi Scan

Select your network name from the list of available wireless networks, enter your network password, and click the "Connect" button.

Figure 8 - Wi-Fi Network Access

Figure 8 – Wi-Fi Network Access

If your network name (SSID) does not appear in the list, refresh the list by clicking the "Scan" button.

If the connection is successful, the analyzer’s IP parameters will be displayed. Click "Save and Exit" to complete the configuration.

Figure 9 - Network Connection

Figure 9 – Network Connection

Access the device’s integrated web interface using the IP address obtained during the connection process and continue configuring the analyzer parameters.

For stable operation, the Wi-Fi signal level should be greater than -70 dB.

Measurement data is transmitted to the cloud. Data access is provided through the Web Dashboard.

Functions

Analyzer Features

The analyzer measures line current and voltage and displays RMS values in real time. It also calculates power factor, active power, reactive power, and apparent power.

Energy Readings

The analyzer calculates and stores total and partial energy values for active, reactive, and apparent energy.

Energy values can be viewed on the display. The energy unit automatically changes from kWh to MWh (and from kVAh to MVARh) according to the measured value.

Analyzer Operation

Overview

The analyzer features a front panel that includes a status LED indicator, a color graphic display, and a set of contextual function buttons.

These elements allow the operator to intuitively access operational information and to view, configure, and modify operating parameters according to application requirements.

The navigation menu allows users to view, configure, and reset parameters.

Display Screen Overview

Analyzer
AWi-Fi Signal Strength and SSID
BTime – Local Format [HH:MM:SS]
CScreen Content
DWi-Fi Interface IP Address
EStatus Notifications

Status Information

The status LED on the front panel indicates the current operating status of the analyzer.

The icons in the following table indicate the LED status:

LED off = OffLED standby = FlashingLED standby = SolidLED on = Solid
Status LED Status LEDAnalyzer Powered OffStartup PhaseNot ConnectedAnalyzer Connected

Reset and Factory Settings Restoration

To restore the factory Wi-Fi or password settings, proceed as follows:

  • Disconnect power from the device and then restore power. During startup, simultaneously press and hold the UP and DOWN buttons until a confirmation message appears on the display indicating that the Wi-Fi configuration and password have been restored to factory defaults.

Figure 10 – Wi-Fi and Password Factory Reset

Maintenance and Troubleshooting

Overview

The analyzer contains no user-serviceable components. For maintenance or repair operations, please contact technical support at support@renua.it.

Notice
RISK OF DAMAGE TO THE ENERGY ANALYZER
  • Do not open the analyzer enclosure.
  • Do not attempt to repair analyzer components.
Failure to follow these instructions may result in equipment damage.

Do not open the analyzer. Opening the analyzer voids the warranty.

Diagnostic Codes

If anomalies are indicated by the status LED and/or error icons on the display, the system will automatically show a diagnostic code corresponding to the detected condition. If the issue persists after applying the recommended corrective actions, contact technical support.

Diagnostic CodeRE-211DescriptionPossible Solution
-Status LED appears to be offRestart the analyzer by powering it off and on again
-Buttons do not respondRestart the analyzer by powering it off and on again

Maintenance and Troubleshooting

Diagnostic CodeRE-211DescriptionPossible Solution
001The analyzer stops due to an internal errorRestart the analyzer by powering it off and on again
002The analyzer is operating. Frequency settings do not match measured frequencyCorrect the frequency settings according to the nominal network frequency
003The analyzer is operating. Wiring settings do not match wiring inputsCorrect the wiring settings according to the actual wiring inputs
004The analyzer is operating. Phase sequence is reversedCheck cable connections or correct the wiring settings
005The analyzer is operating. Date and time have been reset due to a power interruptionRestart the analyzer by powering it off and on again. Verify the device's Internet connection